Construction of both the new rail tubes on the $16 billion Hudson Tunnel project is officially in progress, the Gateway Development Commission confirmed during a Wednesday board meeting.
Crews launched the second tunnel boring machine last week, starting excavation of the southern tube, said Jim Starace, GDC chief of program delivery, during the meeting. The first machine in the northern tube began work in October and has already bored about 400 feet and installed more than 60 rings of tunnel lining, according to a Wednesday GDC release.
“The start of the tunnel boring this fall was our major milestone, but it was only the beginning,” said GDC CEO Tom Prendergast during the board meeting. “We recently launched our second tunnel boring machine, and we now have officially started building both of the new tunnels’ tubes in the Palisades.”
The two machines will excavate the first 5,100 feet of each tube, from the tunnel portal in North Bergen, New Jersey, to the Hudson County Access Shaft on the border of Weehawken and Hoboken, according to the GDC.
A joint venture of Schiavone Construction, Lane Construction and Dragados leads the Palisades Tunnel package, which includes the excavation and the access shaft. The Port Authority of New York and New Jersey is managing delivery of the package in partnership with GDC.
“The second one is really just beginning. The production rate is increasing as the work continues and as the operation continues,” said Starace during the board meeting. “So, as the production of the TBM continues, we expect a continued increase in production until we come out on the other side in Weehawken.”

Each machine cuts through hard rock and installs the permanent lining as it goes. Inside the machine’s shield, a small crane lifts precast concrete segments into place and workers bolt them together, Starace said during the meeting.
At the other end of the Palisades section, crews have dug about 50 feet to 60 feet down at the access shaft and reached rock, added Starace. He expects the shaft to be complete and the machines to break through around this time next year.
Crews will then remove the machines and bring in a second pair designed for the ground beneath the Hudson River. Boring on that section is slated to begin in 2028, he said.