Dive Brief:
- A Skanska and Traylor Bros. joint venture has delivered a $1.6 billion rail bridge project in New Jersey, according to a Monday news release from Amtrak.
- Gov. Mikie Sherrill and New Jersey Transit Corp. officials commemorated the completion of the Portal North Bridge on Monday and marked the retirement of the 116-year-old swing bridge over the Hackensack River.
- The construction team first won the contract from NJ Transit to construct a two-track span in October 2021. Regular service resumed on Sunday.
Dive Insight:
NJ Transit and Amtrak customers will now have more reliable infrastructure, per the release. The previous draw bridge was notorious for getting stuck in the open position, which caused delays for commuters that cascaded throughout the corridor.
The new, 2.4-mile Portal North Bridge, constructed next to the original, is a fixed span that rises 50 feet above the Hackensack, according to Amtrak. That means it does not have to open for marine traffic to pass under.
Project work included constructing retaining walls, deep foundations, concrete piers, structural steel bridge spans, rail systems and demolition of the existing bridge, which is set for dismantling in 2027, per the release.
To deliver the bridge, the construction team barged three, 400-foot-long, 500-million-pound bridge arches down the Hudson River, according to the Skanska project page. That meant assembling the network-tied arch bridges in Albany, using heavy lift equipment to drive them up onto barges and floating them about 30 hours down the Hudson and Hackensack Rivers under 18 different bridges, per Skanska.
Assembly required 60 cable hangers per arch, with each cable hanger consisting of 31 strands of cable. Crews also installed sidewalk brackets during prefab, laying the foundation for formwork and concrete.
By incorporating electricians and carpenters into the prefabrication process, Skanska says it saved time and reduced hazards.
Overall, the build used:
- 45 million pounds of steel.
- 219,000 cubic yards of concrete.
- Over 35 miles of pipe piles.
- Over 3 miles of drilled shafts.
- 4,850 linear feet of retaining walls.
- 3,289 linear feet of construction access platforms.
“Bringing the Portal North Bridge into full service is a significant milestone for the region and a testament to what can be accomplished through collaboration, innovation and complex infrastructure delivery,” Laszlo Borhi, Skanska project executive, told Construction Dive via email.