FlatironDragados has reached substantial completion on a $133 million segment of a larger, billion-dollar North Carolina highway project, according to the contractor.
The infrastructure giant hit the milestone on the Winston-Salem Northern Beltway Eastern Section, according to the announcement, which is now open to the public. The highway section is one part of the $1.74 billion, 34.5 mile Winston-Salem Northern Beltway, which will begin at U.S. Highway 158 southwest of the city and will end at Interstate 74 to its southeast.
The Eastern Section project features more than 1 1/2 miles of new roadway, seven new bridges and one new interchange.
The project links U.S. Highway 52, a north-south corridor bisecting the state, to the eastern and southeastern side of Winston-Salem. This will divert traffic from downtown and complete the I-74 corridor on the east side of Forsyth County, according to the release.
Winston-Salem, home of Wake Forest University, is a major metro in the Tar Heel State with approximately 257,000 residents, according to census data. More than 100,000 vehicles and trucks travel through the area daily, which is more than current roadways are designed to handle, according to the North Carolina Department of Transportation.
Next steps on the project are dedicated to funding and constructing the remaining segments on the Western Loop, according to an NCDOT table detailing project segments.
The investment in road infrastructure puts North Carolina’s highways ahead of the curve, nationally. In January, the American Society of Civil Engineers gave the state’s road infrastructure a “C-” in its state report card, produced by the ASCE’s North Carolina section. That rating is higher than the U.S. average of a D+ in 2025.
Some of FlatironDragados’ other current road projects include the $4.6 billion State Route 400 Express Lanes project in Georgia alongside Acciona Construction and a $323 million roadway job at Los Angeles International Airport, a joint venture with Skanska.