Tom Black is executive vice president at Ladson, South Carolina-based Frampton Construction. Opinions are the author’s own.
Most contractors’ pursuit teams are enthusiastic and optimistic about jobs and contract terms. That’s healthy, but some pursuits pit two goals against each other: winning revenue now and protecting the company’s long-term health. My job is to weigh the two before anyone signs.
A signed contract isn't a successful job; it’s only the beginning. Leaders who confuse willingness to sign with the ability to deliver might be betting the company on a single project.
A good contract leaves both parties reasonably uncomfortable. For a general contractor, the question is whether that discomfort reflects a hard negotiation or an obligation the business cannot reasonably carry.
I've seen owners try to shift that kind of risk onto general contractors often in my career. But the stakes have changed. Projects are larger and more complex, owners are more sophisticated and the consequences of a bad term are bigger for everyone.
At Frampton, four high-risk terms come up again and again. We’ve reached common ground with owners on every single one, including in contracts we never would have signed as first written. Here’s how I weigh it.
1. Don’t accept unknown conditions as defined scope
You can’t price what you can’t see. Still, some owners put responsibility on general contractors for hidden conditions, like infrastructure behind a wall or the site’s soil that was sampled only by a 3-inch bore every 100 feet.

When that happens, we, as contractors, must protect our business by building contingency into the price. Under a fixed or guaranteed price, the owner ends up paying for it whether or not the problem ever appears.
For contractors, finding common ground means defining what the price includes, what remains unknown and how the team will handle those conditions if they arise. Allowances and contingencies can help quantify uncertainty, but the contract still needs a clear allocation of responsibility for conditions the team cannot reasonably evaluate.
2. Don’t accept responsibility without authority
The riskiest obligations make a contractor responsible for something it doesn’t control. This most commonly happens in terms that flow down to trade partners and the area of design responsibility.
When an owner holds an overly aggressive line, contractors need to consider how those obligations will affect their ability to assemble a qualified trade team. Terms that flow down to subcontractors may drive capable firms away or lead them to price in the added risk.
Before signing, general contractors need to know which obligations their trade partners will accept and what exposure they will retain if those partners cannot carry them. Any obligation those partners can’t carry falls back on the general contractor, which has no control over it.
Design responsibility is another common example we see where risk can shift to the general contractor. When an owner retains its own architects and engineers, those firms are obligated to produce documents a contractor can build from. Yet custom contracts often make the contractor responsible for anything "reasonably inferable" from incomplete documents or for everything necessary to deliver a "complete operating system" it didn't design.
We build to the design, coordinate the trades and flag gaps in the documents when we see them. But a contractor can’t take on responsibility for decisions that belong to the design team. When performance depends on a design we don’t control, accountability must stay with the people who made those decisions.
Responsibility should align with authority and a clearly defined scope. If a contractor can’t control an outcome, it shouldn’t own it.
3. Don’t agree to requirements your team can’t realistically meet
Some terms can look reasonable on paper and fall apart on site. Notice provisions are the most common example. Notices are always about time or money, and missing a deadline can mean forfeiting your right to either. Industry template contracts generally allow 21 days, but I’m seeing more and more custom contracts that require notice within 24 to 36 hours and waive the claim entirely if it's late.
That’s not how a jobsite works. A project manager may have a thousand things going on and a serious problem to solve, or an issue may surface the Thursday before a holiday weekend. Meeting a 24- to 36-hour deadline in those moments isn’t realistic. Before accepting that requirement, contractors need to assess whether their teams can consistently meet it and what additional staffing or processes it would take to comply. Otherwise, they risk signing away the right to recover time or money before they understand the full impact of a problem.
Liquidated damages raise the same problem. They’re a normal part of construction contracts, but they become a significant issue when they’re set high and ignore what the contractor can’t control: owner decisions, design releases, utility service, site access and owner-furnished equipment.
When those dependencies slip without relief, contractors turn to overtime, trade stacking and out-of-sequence work to protect the schedule. Costs climb, and everyone retreats to their corner to take their defensive positions instead of solving the problem.
Contractors should negotiate notice periods their teams can realistically meet and clear rights to schedule relief when delays fall outside their control. Those protections need to be in the contract before work begins.
4. Don’t agree to liability that exceeds insurance and financial capacity
Contractors expect to indemnify owners for their own mistakes, and we pay a lot of money to insure that obligation. Owners usually set those insurance limits themselves. The danger comes when broad indemnity obligations or exposure to substantial business losses can exceed those limits.
At that point, the general contractor isn’t risking a project; they’re risking their business. Before signing, leadership needs to understand which obligations insurance will cover and which could fall directly on the company.
Contractors need to explain that these obligations can leave owners exposed, too. An obligation offers little protection if the contractor lacks both the insurance and the financial capacity to cover it. If something catastrophic happens, the owner needs a realistic source of recovery. That gives contractors a practical reason to push for obligations that align with available insurance and the risks they can reasonably carry.
I consider indemnity obligations that stay within insurable limits and a mutual waiver of consequential damages gold standard provisions. We've walked away from projects that didn't include that waiver. If you can’t find common ground, don’t put your business at risk.
Common ground starts with knowing your limits
Reaching common ground on all four isn't luck. It happens because each side explains what it can and can't carry and because leadership knows its limits before a pursuit builds momentum. Eager teams want the job. Part of my role is helping them step back, look at what the obligations really mean and temper that excitement when the terms aren't reasonable. "We need the work" is how contractors end up signing impossible contract terms or promising work they can't deliver.
The owner's goal is to deliver a project with a predictable outcome, a dependable cost and a dependable schedule. Contract terms should support that outcome. Contractors best serve that goal by signing only what they can deliver and having the discipline to walk away when they can't.